Auditing a Validation System
3
on the approved process method and specifications. This phase qualifies process and
procedures and demonstrates that the equipment and ancillary systems do what they
claim to do.
Piping and installation drawings (P&ID): Mechanical drawing or blueprints of the
required piping system for installation of equipment.
Quality risk management: A systematic process for the assessment, control,
communication and review of risks to the quality of the drug (medicinal) product across
the product lifecycle.
Worst Case: Conditions within normal parameters most likely to give failure. For
processing purposes, worst case means those values of normal operating parameters
most likely to cause process failure. For sampling locations, worst case means those
equipment locations most likely to have higher levels of residues after cleaning. For
sampling recovery, worst case means those procedures, within normal sampling
parameters, most likely to give poorer percentage recovery.
Explanation of Topic
Introduction
Validation is the action of proving, in accordance with the principles of GMP, that any
procedure, process, equipment, material activity or system consistently leads to the
expected results. Documented evidence provides a high degree of assurance that a
specific system, equipment or process will consistently produce a product meeting its
pre-determined specifications and quality attributes. To put it simply, validation is
nothing more than proving that a process actually works.
What should be valida
ted?
We use the terms validation and qualification to cover the documented verification of a
spectrum of GMP activities including
· Facilities
· Equipment used in manufacturing
· Equipment used to control the environment(s) where product is manufactured or
stored
· Utilities with product contact (e.g., water systems, compressed gases, air)
· HVAC systems
· Alarm systems that monitor utilities and air handling for process and storage areas
· Analytical methods
· Analytical instruments
· Computerized systems (e.g., computerized training system, documentation control
system)
· Cleaning processes
· Manufacturing processes
Auditing a Validation System
5
likelihood of detection of the failure. Appropriate systems are implemented to ensure that
the theoretical hazards do not present a hazard to the process. The appropriate limits are
set for these systems.
If the risk assessment has been properly carried out and documented, parts of a process
that are low risk may be eliminated or paid minimal attention during validation.
Benefits of validation
Validation assures that the entire manufacturing process and support systems work
properly before actual production begins.
Validation ensures that safe, quality products are consistently manufactured. The
validation process gives the manufacturer a further understanding of the process, possibly
improved operational efficiency, more robust processes, reduced risk of failure and
improved compliance.
General Validation guidelines
The first step to the overall validation process is to define the key requirements of the
product/process, e.g. by documenting the appropriate parameters in a User Requirement
Specification (URS) and a Functional Specification describing what is needed and how
the final result is to be achieved. A design qualification (DQ) is performed to collect
documented verification that the proposed design of facilities is suitable for the intended
purpose.
The total validation process involves DQ, IQ, OQ, PQ, process
validation,
maintenance, change control and revalidation.
Rationales used as basis for validation strategies should be documented.
Validation Stages
Establishing Qualification Process Monitoring and
key (IQ, OQ, Validation Change Control Revalidation
requirements PQ)
Since validation consists of different stages, critical sections of each stage must be
completed before moving to the next stage. Some of these critical sections include
complete testing, investigation of critical deviations and/or exceptions, and repai r (e.g.
wiring connected incorrectly). Deviations must be closed and interim approval of the
stage should be obtained prior to beginning the next stage. The protocol for the next
Auditing a Validation System
7
criteria to be tested against, etc. This directing document is the Validation Plan (VP).
The VP is a strategic document which identifies the elements to be validated, the
approach to be taken for validation of each element, the organizational responsibilities
and the documentation to be produced to ensure full consideration is given to product
quality aspects. It shows how the separate validation activities are organized and
interlinked. Overall it provides the details and relative time scales for the validation work
to be performed.
Specific elements of the VP are qualification/validation methodology, qualification
activities, personnel responsibilities, schedule, preventive maintenance, change control,
relevant SOPs and documentation requirements.
The VP is required to be prepared and approved at an early stage of the project. This plan
may or may not include design installation and operational performance qualification
protocols as individual documents. Not all projects need to be included in a VP. This
document is required when the coordination of many validation activities is necessary.
Examples are:
Ø Construction of a new manufacturing facility
Ø Purchase and installation of a new utility, (e.g. a new purified water system)
Ø Installation of a new packaging line
Ø Significant refurbishment to existing facilities, utilities and equipment
Equipment Qualification
To ensure that a manufacturing or testing process will work properly, the equipment used
in the process must perform reliably and within specifications. To achieve this, the
equipment must be qualified.
Design, installation, operation and performance qualification (DQ/IQ/OQ/PQ) are phases
of validation that support the startup of new, modified, or retrofitted equipment.
DQ/IQ/OQ/PQ studies establish confidence that the equipment and ancillary systems are
capable of consistently operating within the established design and operating limits and
tolerances.
Design Qualification (DQ)
Design qualification (DQ) may be established as a separate process with its own protocol
or may be combined in the Validation Plan. The purpose of this qualification is to assure
that a proposed new or modified facility, system or equipment meets GMP requirements,
is suitable for its intended purpose and defines how the Users Requirement Specification
(URS) are to be met.
The URS establishes agreed and properly defined facilities/utilities/equipment functionality
requirements. Variables should be specified in terms of expected reliability, consistency and
capability.
Auditing a Validation System
9
The protocol should include the roles and responsibilities for IQ development, execution,
assurance of completion and maintenance. It should identify functional groups required
to review and approve the protocol. Functional groups should include those who can
provide a technical evaluation (e.g., Engineering, Maintenance) and QA. QA should
always be an approver to ensure that all GMP and regulatory requirements have been
considered, met, and documented as appropriate. If all critical items in the protocol have
been addressed and approved, but there are some remaining items, the next phase of
qualification may be executed provided that there is written documentation to justify it.
The IQ protocol should include piping and instrumentation diagrams (P & ID), HVAC
drawings and equipment drawings.
Installation Qualification Execution
Installation qualification (IQ) occurs during the equipment installation phase. Equipment
is compared to the original design and installation plans, found either in the Purchase
Order or design specification. This phase ensures that the manufacturer s and the
company s engineering specifications agree. Equipment type and "as – built" conditions
are verified against the design specifications. During this phase, materials of construction,
manufacturer s identification (serial number) are verified against the purchase
specifications and the manufacturer s specifications.
During the installation qualification, utilities completion and calibration take place. The
utilities, (electrical, water, steam, vacuum, compressed gases and HVAC) are checked to
determine if they are connected properly. Wiring installation of electrical lines (loop
checks) is conducted. Software that is used in a computer is checked for the correct
version and that it is installed correctly.
Instruments are also calibrated to verify that indicators for temperature, pressure, flow,
weight, volume, etc. are accurate. Piping systems are reviewed to verify that they have
been correctly installed and that the composition of materials is in agreement with the
design specifications. Piping systems are also reviewed to ensure that the lines have been
degreased, and passivated, if the water systems use stainless steel piping. Piping should
also be identified and tagged.
The installation qualification should include a review of pertinent maintenance
procedures; repair parts lists, and calibration methods for each piece of equipment. The
objective is to assure that all repairs can be performed in such a way that will not affect
the characteristics of material processed after the repair. In addition, special post -repair
cleaning and calibration requirements should be developed to prevent inadvertent
manufacture a of non-conforming product
Information from the installation qualification should be used to:
Ø develop written procedures on calibration
Ø establish a preventative maintenance program
Ø determine which calibration, maintenance and adjustment requirements could
affect the process and product.
Auditing a Validation System
11
Performance Qualification Execution
Performance qualification is a bridge between Operational Qualification and Process
Validation. In Performance Qualification, production materials, qualified substitutes, or
simulated product may be used to test the upper and lower operation limits or worst
case conditions. Performance Qualification is a test of the overall system, with
equipment and ancillary systems tested together.
Process Validation
Process Validation includes establishing documented evidence, which provides a high
degree of assurance that a specific process will consistently produce a product meeting its
pre-determined specifications and quality characteristics.
A predetermined number of validation batches should be manufactured to demonstrate
that, under normal conditions and defined ranges of operating parameters, the
commercial scale process appears to make an acceptable product. It should normally
cover the manufacture of at least three consecutive batches of material.
Validation should be performed under conditions to be used for routine manufacture. The
batch size should be the same as or representative of the intended commercial scale
batches. Sampling and testing should be carried out to ensure compliance with the most
stringent requirements.
If the validation batches are intended for commercial use, the conditions under which
they are prepared and manufactured must comply with the GMP requirements.
Prospective process validation should normally be applied to API and to medicinal
products. The general principle is to validate a manufacturing process and the same
process can typically be used for several related products. Rather than to develop a plan
for each product manufactured by a process, it can be possible to develop a plan for that
process instead. There are two general principles that could be applied. Matrix
approach generally means a plan to conduct process validation on different strengths of
the same product. Family approach describes a plan to conduct process validation on
different, but similar products. Either approach must demonstrate that the process is
consistent for all the strengths or products involved. The plan should be designed to
evaluate all likely sources of variation in the products manufactured by the process.
Process validation must be completed, evaluated, documented and approved before
commercial distribution.
Worst Case and Challenge Tests
The process should be challenged by making deliberate changes to demonstrate its
robustness and to define its limits of tolerance. In challenging a process to assess its
adequacy, the conditions should simulate those that could be encountered during actual
production. These tests should be repeated enough times to assure that the results are
meaningful and consistent.
Auditing a Validation System
13
equipment is considered clean prior to use. For modern, highly automated, equipment the
logical sequencing of cleaning activities should be critically reviewed for adherence to
validated procedures. Maximum permitted time for campaign manufacturing should be
included in cleaning validation studies.
Normally an ongoing monitoring program is set up to confirm satisfactory operation
of the established cleaning process. Key process parameters may be reviewed for
automated systems, in other cases monitoring based on swabs/rinse samples or visual
examination may be conducted.
Validation of Analytical (Chemical, Physical and Microbiological) Test
Methods
Validation of methods is performed to confirm that the performance characteristics of a
method meet the requirements for the intended application. An assessment of validation
studies demonstrating that the method is suitable for its intended purpose shall be
documented appropriately.
Test methods described in any submission for manufacturing authorization, including
development pharmaceuticals, in-process control during manufacture, control tests on
intermediate products, control tests on finished products and stability testing should be
appropriately validated for the phase of development before use. Methods used in testing
of commercial finished products, raw material or packaging component must be validated
before use.
Appropriate level of revalidation of methods may be required by regulatory authori ties
when methods are transferred from one site to another, methods are transferred from one
laboratory to another, if significant changes are made in the manufacturing of major
starting materials or if the composition of the finished product is changed .
Methods and equipment described in pharmacopoeias may be considered validated.
Suitability for use of pharmacopeial methods should be established by testing/technical
review and documented. When claiming compliance with pharmacopoeias, unless the
exact method is being used, a cross validation should be performed.
A number of parameters should be considered in validation of quantitative methods.
These parameters include tolerance limits, specificity, accuracy, precision, detection
limit, quantification limit, linearity and range.
Maintenance of Validated Status/Change Control
The suitability of a facility, utility, process or equipment must be maintained through its
operating life. Systems and documentation need to be in place to support this. Such
monitoring systems should include SOPs, performance monitoring, calibration,
maintenance and cleaning, change control, and periodic review by internal audits. Where
no significant changes have been made to the system or process, and a quality review
confirms that the system or process is consistently producing material meeting its
specifications, there is normally no need for revalidation.
Auditing a Validation System
15
· Verify that a Validation Protocol exists for each validation project, which identifies
qualification activities for DQ/IQ/OQ/PQ and their locations.
· If DQ is performed as a separate qualification,
Ø Verify that there is a system to manage the setup of a preventive maintenance
and change control program for new equipment. This management system
may be part of the IQ/OQ process or part of the site s change control system.
· Ensure that the site has performed the following checks during the IQ phase.
Ø For electrical and instrumentation completion,
i Verify that there is documentation of loop checks.
i Verify that the software version installed is documented.
Ø For installation and instrumentation,
i Verify that the delivered equipment and instrumentation meet the defined
specifications of equipment order.
Ø For utilities completion,
i Verify that there is documentation (e.g., a utilities checkli st) of the
connection of utilities to equipment.
Ø For piping systems completion,
i Verify that the system "walk down" was completed.
i Verify that any red line changes to the P&ID's have been submitted.
Ø Verify that the following documentation is correct:
i As built engineering and installation drawings
i calibration documentation
i weld documentation
i material of construction certifications
· Ensure that the Operational Qualification is complete.
Ø Verify that the valve sequencing (e.g. API tanks) is correct by comparing it
against the piping and installation drawing.
Ø Verify that ranges for process and safety alarms have been set according to
process parameters.
Ø Verify that critical alarms are present by comparing the alarms against a list of
critical parameters.
Ø Verify that the range tested in the protocol encompasses the current alarm
condition.
Ø Verify that worst case conditions have been tested for the equipment and
ancillary systems.
· Ensure that the documentation system is operating in full compliance.
Ø Verify that when any protocol has been approved, any changes to the protocol
followed the site s change control process.
· Ensure that the Performance Qualification is complete.
Ø Verify that the testing performed is within established acceptance criteria.
· Ensure that appropriate SOPs and batch documentation are developed for the
equipment and systems being qualified. Ensure that any restrictions to use are
implemented.
validation refers to establishing documented evidence that a process or system, when operated within established parameters, can perform effectively and reproducibly to produce a medicinal product meeting its pre-determined specifications and quality attributes
Subscribe to:
Post Comments (Atom)
Pharmaceutical Validation Documentation Requirements
Pharmaceutical validation is a critical process that ensures that pharmaceutical products meet the desired quality standards and are safe fo...
-
K. Dashora, D. Singh, Swarnlata Saraf and S. Saraf *. Institute of Pharmacy, Pt.RavishankarShuklaUniversity, Raipur 492 010. *Author for ...
-
Validation of the Autoclave is classified into the following 1.0 OQ – Operational Qualification 2.0 PQ – Performance Qualification The valid...
-
Cold storage is a relatively simple cold room that is commonly used to store material between 2[degrees] to 8[degrees]C. Such cold rooms a...